CROFT provided design and construction administration services for the capacity upgrade of an existing data hall from…
CROFT provided design and construction administration services for the capacity upgrade of an existing data hall from 500 kW to 1 MW and a buildout of a 7,000 square-foot dark shell space to a 1 MW data hall. These projects occurred in concurrent years. The buildout project included the addition of standard retail and colocation rack space as well as High-Performance Computing (HPC) racks. Both data halls were built to ASHRAE Data Center Tier II resiliency standards for concurrent maintainability. The electrical systems were designed for 4N/3 redundancy and the mechanical systems were designed for 5N/4 redundancy for both data halls.